A/NE-FTA/261

Click here to view Applications at the Site/Building

Section 16 Application

Application No.

A/NE-FTA/261

Plan Area

Fu Tei Au & Sha Ling

District

Sha Tin, Tai Po & North District

Date of Application Received

24/06/2025

Location

Lots 187 S.A (Part) and 188 (Part) in D.D 52 and Adjoining Government Land, Fu Tei Au, Sheung Shui, New Territories

Proposal

Proposed Temporary Dangerous Goods Godown (Classes 2 to 9 Dangerous Goods) with Ancillary Office and Associated Filling of Land for a Period of 3 Years

Applicant's Submission

[press here]

Notice & Gist of Development Proposal (including Location Plan) (indicative only for section 12A application)

Notice Download newspaper notice

Gist Download Gist

[Note: The Gist may be superseded by a new Gist if Further Information is received]

Expiry Date for Making Comments on Application (No. of Comments on Application Already Received)

25/07/2025 (20)

Application Available for Public Inspection Until (tentative date of meeting)

15/08/2025

Remark

-

Further Information Received on 09/07/2025,14/07/2025
Nature Responses to comments of the Environmental Protection Department and Urban Design and Landscape Section of Planning Department, and enclosing clarification on the background of the application, land status plan, and land register.
Applicant's Submission [press here]
Decision Accepted and Exempted from Publication

Further Information Received on 29/07/2025,30/07/2025
Nature Responses to departmental comments, and enclosing supplementary information on dangerous goods inventory and storage, and revised swept path analysis and layout plan.
Applicant's Submission [press here]
Decision Accepted and Exempted from Publication

Further Information Received on 04/08/2025
Nature Responses to comments of the Environmental Protection Department, and enclosing supplementary information on quantities of dangerous goods to be stored at the application site.
Applicant's Submission [press here]
Decision Accepted and Exempted from Publication

Further Information Received on 08/08/2025,11/08/2025
Nature Responses to comments of the Transport Department, and enclosing revised swept path analysis and layout plan.
Applicant's Submission [press here]
Decision Accepted and Exempted from Publication

Further Information Received on 12/08/2025,13/08/2025
Nature Responses to departmental and public comments, and enclosing supplementary information relating to land matters.
Applicant's Submission [press here]
Decision Accepted and Exempted from Publication